Energy Projects Near You

Oving Solar Farm (5 MW)

Oving Solar Farm is a 5 MW solar farm project in Chichester, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 14 August 2012; the record was last updated on 6 December 2012.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
6 December 2012record last updated
Chichestercouncil area

Planning timeline

DateStage
21 February 2011Application submitted
3 May 2011Planning permission granted
4 May 2012Construction started
14 August 2012Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
6 December 2012
Operator or applicant
Vogt Solar
Planning authority
Chichester
Planning application reference
11/00738/FUL
Site area
17.9 ha
Address (REPD)
Woodhorn Farm, Church Lane, nr.Oving, West Sussex
Council area (by location)
Chichester
Time to decision
10 weeks
REPD reference
1571

Who decides

ApplicationsChichesterUK
Decided applications (solar, wind, battery)2510,236
Refused4 (16%)19%
Solar refused4 of 2412%
Battery storage refused0 of 116%
Median time from submission to decision12.9 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Land at Tangmere Airfieldsolar farm5operational1.2
Decoy Farm House Solar Modulessolar farm6operational1.3
Strettington Solar Farmsolar farm5operational2.8
Merston Solar Parksolar farm10operational2.8
Former Westhampnett Landfillsolar farm7.5operational2.9
Manor Farm - Shripneysolar farm5operational3.0
Boxgrove Common, Tinwood Lanebattery storage70approved, not built3.1
Park Farmsolar farm5operational3.6
Mundham, Runcton Lane Solar Farmsolar farm30approved, not built4.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.8373, -0.7054).