Land at Tangmere Airfield (5 MW solar farm)

Land at Tangmere Airfield is a 5 MW solar farm project in Chichester, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 7 October 2015; the record was last updated on 11 January 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
11 January 2016record last updated
Chichestercouncil area

Planning timeline

DateStage
13 November 2014Application submitted
1 January 2015Planning permission granted
1 August 2015Construction started
7 October 2015Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
11 January 2016
Operator or applicant
West Sussex County Council
Planning authority
Chichester
Planning application reference
14/03894/CPO
Site area
9.1 ha
Address (REPD)
Tangmere Airfield Nurseries, The Old Airfield, Tangmere Road, Tangmere, Chichester
Council area (by location)
Chichester
Time to decision
7 weeks
REPD reference
4766

Who decides

ApplicationsChichesterUK
Decided applications (solar, wind, battery)2510,236
Refused4 (16%)19%
Solar refused4 of 2412%
Battery storage refused0 of 116%
Median time from submission to decision12.9 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Oving Solar Farmsolar farm5operational1.2
Boxgrove Common, Tinwood Lanebattery storage70approved, not built1.9
Strettington Solar Farmsolar farm5operational2.2
Decoy Farm House Solar Modulessolar farm6operational2.2
Former Westhampnett Landfillsolar farm7.5operational2.9
Manor Farm - Shripneysolar farm5operational3.9
Merston Solar Parksolar farm10operational3.9
Park Farmsolar farm5operational4.8
Mundham, Runcton Lane Solar Farmsolar farm30approved, not built5.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.8481, -0.7019).