Energy Projects Near You

Park Farm (5 MW solar farm)

Park Farm is a 5 MW solar farm project in Arun, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 24 March 2016; the record was last updated on 19 April 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
19 April 2016record last updated
Aruncouncil area

Planning timeline

DateStage
23 July 2015Application submitted
29 October 2015Planning permission granted
15 December 2015Construction started
24 March 2016Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
19 April 2016
Operator or applicant
BNRG (BL Solar)
Planning authority
Arun
Planning application reference
P/81/15/PL
Address (REPD)
Land north west of Park Farm, Pagham, Lagness, Chichester
Council area (by location)
Arun
Time to decision
14 weeks
REPD reference
5786

Who decides

ApplicationsArunUK
Decided applications (solar, wind, battery)1110,236
Refused0 (0%)19%
Solar refused0 of 1112%
Median time from submission to decision13.9 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Mundham, Runcton Lane Solar Farmsolar farm30approved, not built1.5
Merston Solar Parksolar farm10operational1.7
Manor Farm - Shripneysolar farm5operational2.6
Decoy Farm House Solar Modulessolar farm6operational3.1
Oving Solar Farmsolar farm5operational3.6
Land at Tangmere Airfieldsolar farm5operational4.8
Former Westhampnett Landfillsolar farm7.5operational5.0
Strettington Solar Farmsolar farm5operational5.8
Bilsham Farmsolar farm14.5operational5.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.8059, -0.717).