Bilsham Farm (14.5 MW solar farm)

Bilsham Farm is a 14.5 MW solar farm project in Arun, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 10 November 2014; the record was last updated on 17 March 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

14.5 MWsolar farm
operationalstatus in REPD
17 March 2015record last updated
Aruncouncil area

Planning timeline

DateStage
4 November 2013Application submitted
13 February 2014Planning permission granted
4 August 2014Construction started
10 November 2014Operational

Project details

Technology
solar farm
Capacity
14.5 MW
Status (REPD)
operational
Record last updated
17 March 2015
Operator or applicant
NextEnergy Solar Fund
Planning authority
Arun
Planning application reference
Y/87/13/
Site area
36.9 ha
Address (REPD)
Land Southwest of Drove Lane Farm Yapton
Council area (by location)
Arun
Time to decision
14 weeks
REPD reference
1966

Who decides

ApplicationsArunUK
Decided applications (solar, wind, battery)1110,236
Refused0 (0%)19%
Solar refused0 of 1112%
Median time from submission to decision13.9 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Binsted Farmsolar farm5operational3.0
Manor Farm - Shripneysolar farm5operational3.3
Decoy Farm House Solar Modulessolar farm6operational4.3
Oving Solar Farmsolar farm5operational5.6
Park Farmsolar farm5operational5.8
Land at Tangmere Airfieldsolar farm5operational6.0
Boxgrove Common, Tinwood Lanebattery storage70approved, not built6.5
Merston Solar Parksolar farm10operational6.8
Mundham, Runcton Lane Solar Farmsolar farm30approved, not built7.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.8138, -0.6357).