Bakers Farm (solar) (12 MW)

Bakers Farm (solar) is a 12 MW solar farm project in Chichester, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 20 March 2015; the record was last updated on 2 August 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

12 MWsolar farm
operationalstatus in REPD
2 August 2016record last updated
Chichestercouncil area

Planning timeline

DateStage
19 March 2014Application submitted
6 October 2014Planning permission granted
30 January 2015Construction started
20 March 2015Operational

Project details

Technology
solar farm
Capacity
12 MW
Status (REPD)
operational
Record last updated
2 August 2016
Operator or applicant
Quercus Renewable Holding 2
Planning authority
Chichester
Planning application reference
14/00870/FULEIA
Site area
21.7 ha
Address (REPD)
Bakers Farm Selsey Road Sidlesham Chichester West Sussex
Council area (by location)
Chichester
Time to decision
29 weeks
REPD reference
1957

Who decides

ApplicationsChichesterUK
Decided applications (solar, wind, battery)2510,236
Refused4 (16%)19%
Solar refused4 of 2412%
Battery storage refused0 of 116%
Median time from submission to decision12.9 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Land At Ferry Farmsolar farm10operational1.0
Ferry Farmsolar farm11approved, not built3.8
Mundham, Runcton Lane Solar Farmsolar farm30approved, not built5.9
Park Farmsolar farm5operational7.1
Merston Solar Parksolar farm10operational7.4
Manor Farm - Shripneysolar farm5operational9.6
Former Westhampnett Landfillsolar farm7.5operational9.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.7644, -0.7931).