Little Gala Wind Farm (30 MW)

Little Gala Wind Farm is a 30 MW wind farm project in South Lanarkshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: appeal withdrawn; the record was last updated on 19 August 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

30 MWwind farm
appeal withdrawnstatus in REPD
19 August 2025record last updated
South Lanarkshirecouncil area

Planning timeline

DateStage
10 June 2022Application submitted
30 September 2024Refused by the planning authority
28 November 2024Appeal lodged
14 July 2025Appeal withdrawn

Project details

Technology
wind farm
Capacity
30 MW
Status (REPD)
appeal withdrawn
Record last updated
19 August 2025
Operator or applicant
BayWa r.e. UK Limited
Planning authority
South Lanarkshire
Planning application reference
P/22/0881
Appeal reference
AP/24/0010
Turbines
6
Turbine height
149 m
Address (REPD)
1km W/O Littlegala Farm B7055 From Wiston A73 To Mountstewart Access Wiston Biggar South Lanarkshire
Council area (by location)
South Lanarkshire
Time to decision
120 weeks
REPD reference
11856

Who decides

ApplicationsSouth LanarkshireUK
Decided applications (solar, wind, battery)8910,236
Refused30 (34%)19%
Solar refused2 of 2012%
Onshore wind refused21 of 5645%
Battery storage refused7 of 1316%
Median time from submission to decision47.4 weeks17.0 weeks
Appeals lodged / allowed6 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Limmer Hillwind farm99application withdrawn2.9
M74 West Renewable Energy Parksolar farm82.5application submitted4.7
M74 West Renewable Energy Parkwind farm165application submitted4.7
Broken Cross (Former Surface Mine)wind farm48operational6.1
M74 West Renewable Energy Parkbattery storage50application submitted6.1
Glentaggart Wind Farmwind farm17appeal withdrawn6.5
Poniel Wind Turbineswind farm9application withdrawn6.6
Coalburn II Energy Storage Facilitybattery storage1,000under construction6.6
High Netherfauld House Farm 1, Tower Roadbattery storage502application submitted6.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.5729, -3.7366).