Lynt Farm (27 MW solar farm)

Lynt Farm is a 27 MW solar farm project in Swindon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2015; the record was last updated on 15 April 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

27 MWsolar farm
operationalstatus in REPD
15 April 2015record last updated
Swindoncouncil area

Planning timeline

DateStage
20 June 2014Application submitted
9 January 2015Planning permission granted
15 January 2015Construction started
31 March 2015Operational

Project details

Technology
solar farm
Capacity
27 MW
Status (REPD)
operational
Record last updated
15 April 2015
Operator or applicant
Meag
Planning authority
Swindon
Planning application reference
S/14/1048
Site area
50.4 ha
Address (REPD)
Land At Lynt Farm, Lynt Farm Lane, Inglesham, Swindon
Council area (by location)
Swindon
Time to decision
29 weeks
REPD reference
2035

Who decides

ApplicationsSwindonUK
Decided applications (solar, wind, battery)4310,236
Refused1 (2%)19%
Solar refused0 of 3512%
Onshore wind refused1 of 145%
Battery storage refused0 of 716%
Median time from submission to decision10.9 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Pentylands Farmsolar farm19operational2.3
Snowswick Lane, Coleshill Solar Farmsolar farm39.6application submitted3.1
Westmill Wind Farmwind farm6.5operational5.7
Corner Copse Solar Farmsolar farm49.9under construction5.9
Stanton solar parksolar farm5operational6.0
Westmill Farmsolar farm5operational6.2
Castle Eaton Farmsolar farm17.8operational6.4
Queenslaine Farm, Highworth Roadbattery storage66approved, not built6.7
Roves Farm (Solar)solar farm12.7operational7.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.6625, -1.7004).