Lynt Farm (27 MW solar farm)
Lynt Farm is a 27 MW solar farm project in Swindon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2015; the record was last updated on 15 April 2015.
27 MWsolar farm
operationalstatus in REPD
15 April 2015record last updated
Swindoncouncil area
Planning timeline
| Date | Stage |
|---|---|
| 20 June 2014 | Application submitted |
| 9 January 2015 | Planning permission granted |
| 15 January 2015 | Construction started |
| 31 March 2015 | Operational |
Project details
- Technology
- solar farm
- Capacity
- 27 MW
- Status (REPD)
- operational
- Record last updated
- 15 April 2015
- Operator or applicant
- Meag
- Planning authority
- Swindon
- Planning application reference
- S/14/1048
- Site area
- 50.4 ha
- Address (REPD)
- Land At Lynt Farm, Lynt Farm Lane, Inglesham, Swindon
- Council area (by location)
- Swindon
- Time to decision
- 29 weeks
- REPD reference
- 2035
Who decides
| Applications | Swindon | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 43 | 10,236 |
| Refused | 1 (2%) | 19% |
| Solar refused | 0 of 35 | 12% |
| Onshore wind refused | 1 of 1 | 45% |
| Battery storage refused | 0 of 7 | 16% |
| Median time from submission to decision | 10.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 0 / 0 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Pentylands Farm | solar farm | 19 | operational | 2.3 |
| Snowswick Lane, Coleshill Solar Farm | solar farm | 39.6 | application submitted | 3.1 |
| Westmill Wind Farm | wind farm | 6.5 | operational | 5.7 |
| Corner Copse Solar Farm | solar farm | 49.9 | under construction | 5.9 |
| Stanton solar park | solar farm | 5 | operational | 6.0 |
| Westmill Farm | solar farm | 5 | operational | 6.2 |
| Castle Eaton Farm | solar farm | 17.8 | operational | 6.4 |
| Queenslaine Farm, Highworth Road | battery storage | 66 | approved, not built | 6.7 |
| Roves Farm (Solar) | solar farm | 12.7 | operational | 7.2 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.6625, -1.7004).