Rock Farm Solar Farm (12 MW)

Rock Farm Solar Farm is a 12 MW battery storage project in Shropshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 January 2026; the record was last updated on 19 May 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

12 MWbattery storage
under constructionstatus in REPD
19 May 2026record last updated
Shropshirecouncil area

Planning timeline

DateStage
2 December 2022Application submitted
25 September 2023Planning permission granted
1 January 2026Construction started

Project details

Technology
battery storage (co-located with re)
Capacity
12 MW
Status (REPD)
under construction
Record last updated
19 May 2026
Operator or applicant
Enviromena
Planning authority
Shropshire
Planning application reference
22/05424/EIA
Address (REPD)
SE Of Rock Farm Rocks Green Ludlow
Council area (by location)
Shropshire
Time to decision
42 weeks
Name in REPD
Rock Farm - Solar Farm
REPD reference
15248

The scheme also includes 12 MW of battery storage, recorded separately in REPD (under construction).

Who decides

ApplicationsShropshireUK
Decided applications (solar, wind, battery)9810,236
Refused22 (22%)19%
Solar refused20 of 7812%
Onshore wind refused2 of 345%
Battery storage refused0 of 1716%
Median time from submission to decision15.2 weeks17.0 weeks
Appeals lodged / allowed10 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Rock Farm Solar Farmsolar farm40under construction<0.1
South of Henley Hallsolar farm5operational1.7
Squirrel Lane Solar Photovoltaic Farmsolar farm12operational2.2
Steventon Roadbattery storage23approved, not built3.1
Whitton Solar Farmsolar farm8.6refused on appeal4.6
Brick House Farm Solar Farmsolar farm49.9approved, not built7.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.3777, -2.6996).