Squirrel Lane Solar Photovoltaic Farm (12 MW)

Squirrel Lane Solar Photovoltaic Farm is a 12 MW solar farm project in Shropshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 May 2026; the record was last updated on 3 June 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

12 MWsolar farm
operationalstatus in REPD
3 June 2026record last updated
Shropshirecouncil area

Planning timeline

DateStage
31 May 2022Application submitted
13 October 2022Refused by the planning authority
17 March 2023Appeal lodged
7 July 2023Planning permission granted
7 July 2023Appeal allowed
1 May 2026Operational

Project details

Technology
solar farm
Capacity
12 MW
Status (REPD)
operational
Record last updated
3 June 2026
Operator or applicant
Locogen Limited
Planning authority
Shropshire
Planning application reference
22/02151/FUL
Appeal reference
23/03135/REF
Site area
28.5 ha
Address (REPD)
E/O Squirrel Lane, Ledwyche, Ludlow
Council area (by location)
Shropshire
Time to decision
57 weeks
Contracts for Difference
AR6
Name in REPD
Squirrel Lane - Solar Photovoltaic Farm
REPD reference
9826

Who decides

ApplicationsShropshireUK
Decided applications (solar, wind, battery)9810,236
Refused22 (22%)19%
Solar refused20 of 7812%
Onshore wind refused2 of 345%
Battery storage refused0 of 1716%
Median time from submission to decision15.2 weeks17.0 weeks
Appeals lodged / allowed10 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
South of Henley Hallsolar farm5operational0.8
Rock Farm Solar Farmbattery storage12under construction2.2
Rock Farm Solar Farmsolar farm40under construction2.2
Whitton Solar Farmsolar farm8.6refused on appeal2.8
Steventon Roadbattery storage23approved, not built3.8
Brick House Farm Solar Farmsolar farm49.9approved, not built5.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.3759, -2.667).