Steventon Road (23 MW battery storage)

Steventon Road is a 23 MW battery storage project in Shropshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 30 August 2024, not yet built; the record was last updated on 9 September 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

23 MWbattery storage
approved, not builtstatus in REPD
9 September 2024record last updated
Shropshirecouncil area

Planning timeline

DateStage
21 June 2024Application submitted
30 August 2024Planning permission granted
30 August 2027Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
23 MW
Status (REPD)
approved, not built
Record last updated
9 September 2024
Operator or applicant
Greenfield Company
Planning authority
Shropshire
Planning application reference
24/02223/FUL
Address (REPD)
Steventon Manor, Steventon Road, Ludlow
Council area (by location)
Shropshire
Time to decision
10 weeks
Name in REPD
Steventon Road - Battery Energy Storage
REPD reference
16590

Who decides

ApplicationsShropshireUK
Decided applications (solar, wind, battery)9810,236
Refused22 (22%)19%
Solar refused20 of 7812%
Onshore wind refused2 of 345%
Battery storage refused0 of 1716%
Median time from submission to decision15.2 weeks17.0 weeks
Appeals lodged / allowed10 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Rock Farm Solar Farmbattery storage12under construction3.1
Rock Farm Solar Farmsolar farm40under construction3.1
Squirrel Lane Solar Photovoltaic Farmsolar farm12operational3.8
South of Henley Hallsolar farm5operational3.9
Whitton Solar Farmsolar farm8.6refused on appeal4.3
Brick House Farm Solar Farmsolar farm49.9approved, not built5.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.3499, -2.7032).