Energy Projects Near You

Brick House Farm Solar Farm (49.9 MW)

Brick House Farm Solar Farm is a 49.9 MW solar farm project in Shropshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 21 October 2022, not yet built; the record was last updated on 29 September 2025. REPD records the planning permission as expiring on 21 October 2025, but the project holds a Contracts for Difference award (AR5), so construction may have started. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
approved, not builtmay be out of datestatus in REPD
29 September 2025record last updated
Shropshirecouncil area

REPD records the planning permission as expiring on 21 October 2025, but the project holds a Contracts for Difference award (AR5), so construction may have started.

Planning timeline

DateStage
1 June 2022Application submitted
21 October 2022Planning permission granted
21 October 2025Permission expired

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
29 September 2025
Operator or applicant
Bluefield Renewwable Developments Limited
Planning authority
Shropshire
Planning application reference
22/02565/FUL
Site area
54.0 ha
Address (REPD)
Brick House Farm Greete Ludlow
Council area (by location)
Shropshire
Time to decision
20 weeks
Contracts for Difference
AR5
Name in REPD
Brick House Farm - Solar Farm
REPD reference
10513

Who decides

ApplicationsShropshireUK
Decided applications (solar, wind, battery)9810,236
Refused22 (22%)19%
Solar refused20 of 7812%
Onshore wind refused2 of 345%
Battery storage refused0 of 1716%
Median time from submission to decision15.2 weeks17.0 weeks
Appeals lodged / allowed10 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Whitton Solar Farmsolar farm8.6refused on appeal2.9
Squirrel Lane Solar Photovoltaic Farmsolar farm12operational5.6
Steventon Roadbattery storage23approved, not built5.6
The Waddings, Knighton-On-Temebattery storage60application submitted5.8
South of Henley Hallsolar farm5operational6.3
Rock Farm Solar Farmsolar farm40under construction7.1
Rock Farm Solar Farmbattery storage12under construction7.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.3331, -2.6249).