Thanet (extension) offshore wind farm

Thanet (extension) is a 340 MW offshore wind farm with 34 turbines in English waters. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 1 June 2020; the record was last updated on 29 June 2020. Its REPD grid reference is 11 km from the nearest postcode on land (CT10 3PE, Thanet). It was consented under Section 36 of the Electricity Act 1989 by the Secretary of State for energy (REPD: DECC, the energy department at the time).

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

340 MWoffshore wind farm
refusedstatus in REPD
29 June 2020record last updated
11 km from land (Thanet)REPD location

Consent timeline

DateStage
27 June 2018Application submitted
1 June 2020Refused by the planning authority

Project details

Technology
offshore wind farm
Capacity
340 MW
Turbines
34
Turbine capacity
10 MW
Turbine height
210 m
Status (REPD)
refused
Record last updated
29 June 2020
Operator or applicant
Vattenfall
Consenting authority (REPD)
DECC (S36)
Application reference
not recorded
Nearest postcode on land
CT10 3PE (Thanet), 11.2 km from the REPD grid reference
Time to decision
101 weeks
REPD reference
6299

Who decides

It was consented under Section 36 of the Electricity Act 1989 by the Secretary of State for energy (REPD: DECC, the energy department at the time).

Postcode districts within 40 km

Districtkm
Broadstairs (CT10)13.0
Margate (CT9)14.7
Ramsgate (CT11)15.6
Ramsgate (CT12)17.8
Westgate-on-Sea (CT8)18.3
Birchington (CT7)21.4
Sandwich (CT13)25.3
Deal (CT14)26.9
Canterbury (CT3)31.0
Herne Bay (CT6)32.7
Dover (CT15)35.0
Dover (CT16)37.0

Straight-line distance from the centre of each postcode district to the REPD grid reference of the wind farm, which is a single point for the whole site.

Other offshore wind projects within 30 km

ProjectMWStatuskm
Thanet300operational3.0
London Array Phase 1630operational23.3

All offshore wind farms in UK waters

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database can lag behind consent decisions. Location: REPD grid reference (51.4206, 1.5927).