Energy Projects Near You

Westerfield Farm (12.5 MW solar farm)

Westerfield Farm is a 12.5 MW solar farm project in West Oxfordshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 25 March 2015; the record was last updated on 14 May 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

12.5 MWsolar farm
operationalstatus in REPD
14 May 2015record last updated
West Oxfordshirecouncil area

Planning timeline

DateStage
29 October 2013Application submitted
23 January 2014Refused by the planning authority
27 February 2014Appeal lodged
1 December 2014Planning permission granted
1 December 2014Appeal allowed
4 February 2015Construction started
25 March 2015Operational

Project details

Technology
solar farm
Capacity
12.5 MW
Status (REPD)
operational
Record last updated
14 May 2015
Operator or applicant
Lightsource Renewable Energy
Planning authority
West Oxfordshire
Planning application reference
13/1534/P/FP
Appeal reference
APP/D3125/A/14/2214281
Site area
28.4 ha
Address (REPD)
Westerfield Farm, Carterton
Council area (by location)
West Oxfordshire
Time to decision
57 weeks
REPD reference
2089

Earlier applications for this site

ApplicationMWSubmittedOutcome
Westerfield Farm 13/1129/P/FP129 August 2013refused 22 October 2013

Who decides

ApplicationsWest OxfordshireUK
Decided applications (solar, wind, battery)3410,236
Refused11 (32%)19%
Solar refused9 of 2612%
Battery storage refused2 of 816%
Median time from submission to decision17.0 weeks17.0 weeks
Appeals lodged / allowed3 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Shilton Downs Solar Parksolar farm5refused on appeal1.4
Shilton Road Solar Parksolar farm8approved, not built2.2
Ventura Parkbattery storage7abandoned2.4
Kencot Hill Solar Farmsolar farm37operational3.6
Caswell Lane, Brize Norton Solar Farm & Battery Storagesolar farm30application submitted4.8
Ducklington Solar Farmsolar farm36under construction7.5
Aston Road, Aston Solar Panels & Battery Energy Storage Systemsolar farm40application submitted8.6
Quarry Solar Farm & Battery Storage Facilitysolar farm35approved, not built8.6
Quarry Solar Farm & Battery Storage Facilitybattery storage35approved, not built8.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.7854, -1.6082).