Energy Projects Near You

Solar, wind and battery projects near Glasgow (G4)

42 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of G4 (Glasgow City): 3 are waiting for a planning decision, 30 approved but not yet running, 2 operational. The largest live scheme is Whitehill Energy Storage (200 MW battery storage, approved on 28 October 2024, not yet built), 1.0 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

42projects within 10 km
3awaiting a decision
30approved, not running
2operational

Projects within 10 km of G4

Projects of 1 MW and more (14)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Whitehill Energy Storagebattery storagebattery storage200approved, not builtupdated Dec 2024Oct 2022granted Oct 2024Dec 2024Glasgow City1.0
Broomloan Roadbattery storagebattery storage49.9approved, not builtupdated Oct 2024Mar 2024granted Oct 2024Oct 2024Glasgow City4.1
Seath Road, Rutherglenbattery storagebattery storage50refusedupdated Apr 2024Sep 2023refused Mar 2024Apr 2024South Lanarkshire4.3
Downiebrae Road, Rutherglenbattery storagebattery storage150approved, not builtupdated Oct 2025Jan 2025granted Sep 2025Oct 2025Glasgow City4.4
Govan Battery Energy Storage Systembattery storagebattery storage49.9application submittedupdated Mar 2025Feb 2025—Mar 2025Glasgow City4.4
Dalmarnock Roadbattery storagebattery storage40approved, not built may be out of dateupdated Mar 2021Sep 2021granted Feb 2022Mar 2021South Lanarkshire4.5
Caledonian Solar Parksolar farmsolar farm18.4approved, not built may be out of dateupdated Nov 2021Oct 2021granted Jun 2023Nov 2021Glasgow City4.6
Kennishead Roadbattery storagebattery storage40application withdrawnupdated Mar 2026Jun 2025—Mar 2026Glasgow City7.8
Cathkin Braes Wind Farm (Castlemilk)wind turbinewind turbine3operationalupdated Sep 2013Sep 2012granted Jan 2013Sep 2013South Lanarkshire8.2
Castlemilk and Carmunnock Community Windpark Trustwind turbinewind turbine2.5refusedupdated Mar 2015Aug 2013refused Nov 2013Mar 2015South Lanarkshire8.9
Highflat Battery Energy Storagebattery storagebattery storage19.9application withdrawnupdated Nov 2018Apr 2018—Nov 2018South Lanarkshire9.2
Gilbertfield Farm, Gilbertfield Roadbattery storagebattery storage40refusedupdated Dec 2025Apr 2025refused Oct 2025Dec 2025South Lanarkshire9.4
Newton Farm, Westburn Roadbattery storagebattery storage40refusedupdated Apr 2026Jul 2025refused Feb 2026Apr 2026South Lanarkshire9.8
Saturland Farm, Salterland Roadbattery storagebattery storage60.8approved, not builtupdated Apr 2025Nov 2023granted Dec 2024Apr 2025Glasgow City9.9
Smaller schemes under 1 MW, mostly rooftop solar (28)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Glasgow Royal Concert Hall, Sauchiehall Streetrooftop solarrooftop solar0.2approved, not builtupdated Mar 2026Oct 2025granted Jan 2026Mar 2026Glasgow City0.3
Garscube Roadrooftop solarrooftop solar0.5approved, not built may be out of dateupdated Jun 2023May 2023granted Jun 2023Jun 2023Glasgow City0.7
The Curran Building, St James Roadrooftop solarrooftop solar0.1approved, not built may be out of dateupdated Dec 2022Aug 2022granted Nov 2022Dec 2022Glasgow City0.9
Duke Street Solar Panelsrooftop solarrooftop solar—approved, not built may be out of dateupdated Mar 2021Feb 2021granted Mar 2021Mar 2021Glasgow City1.3
Sheriff Court Of Glasgow, Carlton Placerooftop solarrooftop solar0.2approved, not builtupdated May 2025Feb 2025granted Apr 2025May 2025Glasgow City1.6
Morrison Bowmore Distillery, Carlisle Street Solar solar PV Systemrooftop solarrooftop solar0.2approved, not builtupdated Nov 2023Sep 2023granted Nov 2023Nov 2023Glasgow City1.9
Kelvin Hall Sports Arena, Argyle Streetrooftop solarrooftop solar0.6approved, not builtupdated Aug 2024Jun 2024granted Aug 2024Aug 2024Glasgow City2.6
Argyle Streetrooftop solarrooftop solar0.6approved, not builtupdated Apr 2025Feb 2025granted Mar 2025Apr 2025Glasgow City2.6
Balmore Roadrooftop solarrooftop solar0.2approved, not built may be out of dateupdated May 2023May 2023granted Jul 2023May 2023Glasgow City2.7
Hutchesons Grammar Schoolrooftop solarrooftop solar0.2operationalupdated May 2023Mar 2020granted Jun 2020May 2023Glasgow City3.9
Dalmarnock Wastewater Treatment Worksrooftop solarrooftop solar—approved, not built may be out of dateupdated May 2021Apr 2021granted Jun 2021May 2021Glasgow City4.0
Clyde Gateway Developments Limited - D2 Grids Demonstrator Projectsolar farmsolar farm—application submitted may be out of dateupdated Feb 2022Dec 2022—Feb 2022South Lanarkshire4.1
Helen Streetrooftop solarrooftop solar0.3approved, not builtupdated Nov 2023Jul 2023granted Oct 2023Nov 2023Glasgow City4.1
Shipyard, Govan Roadrooftop solarrooftop solar0.8approved, not builtupdated Jul 2024Mar 2024granted Jul 2024Jul 2024Glasgow City4.3
Clyde Gateway Trade Park, Dalmarnock Roadbattery storagebattery storage—application submittedMay 2026——South Lanarkshire4.4
Glasgow High School, Crow Roadrooftop solarrooftop solar0.2approved, not builtupdated Aug 2025May 2025granted Jul 2025Aug 2025Glasgow City5.2
Cunninghame Road, Farm Castle Industrial Estaterooftop solarrooftop solar0.2approved, not built may be out of dateupdated Sep 2022Aug 2022granted Sep 2022Sep 2022South Lanarkshire5.3
Fifty Pitches Placerooftop solarrooftop solar0.5approved, not builtupdated Dec 2023Aug 2023granted Dec 2023Dec 2023Glasgow City6.1
Cambuslang Investment Park, Clydesmill Roadrooftop solarrooftop solar0.5approved, not builtupdated Sep 2023Jul 2023granted Sep 2023Sep 2023Glasgow City6.5
Shipyardrooftop solarrooftop solar0.5approved, not built may be out of dateupdated Jun 2023Apr 2023granted Jun 2023Jun 2023Glasgow City7.0
Scottish Fire & Rescue Service, Westburn Drive Solar Array & BESSbattery storagebattery storage—approved, not builtupdated May 2026Jan 2026granted Mar 2026May 2026Glasgow City7.4
Decathlon, Old Govan Roadrooftop solarrooftop solar0.2approved, not builtupdated Apr 2024Dec 2023granted Mar 2024Apr 2024Renfrewshire7.5
Westburn Drive, Cambuslangrooftop solarrooftop solar0.3approved, not builtupdated Aug 2023Jun 2023granted Aug 2023Aug 2023South Lanarkshire7.5
Scottish Fire & Rescue Service, Westburn Drive Solar Array & BESSsolar farmsolar farm0.6approved, not builtupdated May 2026Jan 2026granted Mar 2026May 2026South Lanarkshire7.5
Buchanan Gate, Steppssolar farmsolar farm0.9under constructionupdated Oct 2025Apr 2024granted May 2024Oct 2025North Lanarkshire8.2
Allerdyce Roadrooftop solarrooftop solar0.2application withdrawnupdated Jun 2025Dec 2023—Jun 2025Glasgow City8.5
David Lloyd Leisure Health Club, Stewarton Roadrooftop solarrooftop solar0.5approved, not builtupdated Jan 2024Oct 2023granted Dec 2023Jan 2024East Renfrewshire8.8
Glasgow Museums Resource Centre, Woodhead Roadrooftop solarrooftop solar0.2approved, not builtupdated Mar 2025Nov 2024granted Feb 2025Mar 2025Glasgow City9.3

Distance from the average position of the G4 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm4130019.8
Rooftop solar23021106.9
Wind turbine200110
Battery storage132603551

MW in pipeline: pending, approved and under-construction capacity.

How Glasgow City decides solar, wind and battery applications

ApplicationsGlasgow CityUK
Decided applications (solar, wind, battery)2310,236
Refused0 (0%)19%
Solar refused0 of 1912%
Onshore wind refused0 of 145%
Battery storage refused0 of 316%
Median time from submission to decision13.4 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

All projects in Glasgow City

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near G4, 10 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.