Middlerigg (49.9 MW battery storage)

Middlerigg is a 49.9 MW battery storage project in West Lothian, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 22 July 2025, not yet built; the record was last updated on 29 July 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWbattery storage
approved, not builtstatus in REPD
29 July 2025record last updated
West Lothiancouncil area

Planning timeline

DateStage
2 December 2024Application submitted
22 July 2025Planning permission granted
22 July 2028Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
29 July 2025
Operator or applicant
Galileo Green Energy Scotland Limited
Planning authority
West Lothian
Planning application reference
0890/FUL/24
Address (REPD)
Middlerigg
Council area (by location)
West Lothian
Time to decision
33 weeks
Name in REPD
Middlerigg - Battery Energy Storage
REPD reference
16642

Who decides

ApplicationsWest LothianUK
Decided applications (solar, wind, battery)4110,236
Refused5 (12%)19%
Solar refused1 of 1712%
Onshore wind refused4 of 1545%
Battery storage refused0 of 916%
Median time from submission to decision17.1 weeks17.0 weeks
Appeals lodged / allowed3 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Pond Battery Storagebattery storage200approved, not built2.2
Torrance Farm Wind Park Extensionwind farm5.7operational5.4
Torrance Farmwind farm9operational5.7
Heights Road, Blackridge - Woodend Wind Farmwind farm19.8application submitted5.9
Drumduff Wind Farm Extensionwind farm15approved, not built6.2
Burnheadwind farm26operational6.3
Drumduffwind farm8.5operational6.5
Torrance Wind Farm Extension 2wind farm26.4refused6.6
Benhar Windfarmwind farm15refused on appeal8.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.904, -3.6747).