Pond Battery Storage (200 MW)

Pond Battery Storage is a 200 MW battery storage project in West Lothian, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 24 March 2025, not yet built; the record was last updated on 8 April 2025. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

200 MWbattery storage
approved, not builtstatus in REPD
8 April 2025record last updated
West Lothiancouncil area

Planning timeline

DateStage
13 May 2024Application submitted
24 March 2025Section 36 consent granted (Scottish Ministers)
24 March 2030Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
200 MW
Status (REPD)
approved, not built
Record last updated
8 April 2025
Operator or applicant
Banks Renewables
Planning authority
Scottish Government (S36)
Planning application reference
ECU00004765
Address (REPD)
Pond Industrial Park, Whitburn Road, Bathgate
Council area (by location)
West Lothian
Time to decision
45 weeks
Name in REPD
Pond Industrial Park, Whitburn Road - Pond Battery Storage
REPD reference
13404

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Middleriggbattery storage49.9approved, not built2.2
Torrance Farm Wind Park Extensionwind farm5.7operational5.6
Torrance Farmwind farm9operational5.8
Torrance Wind Farm Extension 2wind farm26.4refused6.3
Heights Road, Blackridge - Woodend Wind Farmwind farm19.8application submitted6.6
Drumduff Wind Farm Extensionwind farm15approved, not built7.4
Benhar Windfarmwind farm15refused on appeal7.8
Drumduffwind farm8.5operational7.8
Burnheadwind farm26operational7.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.8868, -3.6575).