Molly Mountain (15 MW wind farm)
Molly Mountain is a 15 MW wind farm project in Fermanagh and Omagh, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 3 December 2014; the record was last updated on 19 March 2015.
15 MWwind farm
operationalstatus in REPD
19 March 2015record last updated
Fermanagh and Omaghcouncil area
Planning timeline
| Date | Stage |
|---|---|
| 15 August 2008 | Application submitted |
| 1 February 2013 | Planning permission granted |
| 30 March 2014 | Construction started |
| 3 December 2014 | Operational |
Project details
- Technology
- wind farm
- Capacity
- 15 MW
- Status (REPD)
- operational
- Record last updated
- 19 March 2015
- Operator or applicant
- Erne Concrete Pumping
- Planning authority
- Fermanagh and Omagh
- Planning application reference
- L/2008/1113/F
- Turbines
- 5
- Address (REPD)
- Land at Molly Mountain near Derrylin
- Council area (by location)
- Fermanagh and Omagh
- Time to decision
- 233 weeks
- REPD reference
- 4066
Who decides
| Applications | Fermanagh and Omagh | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 74 | 10,236 |
| Refused | 12 (16%) | 19% |
| Solar refused | 0 of 1 | 12% |
| Onshore wind refused | 12 of 70 | 45% |
| Battery storage refused | 0 of 3 | 16% |
| Median time from submission to decision | 87.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 8 / 5 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Slieve Rushen Extension | wind farm | 54 | operational | 1.0 |
| Slieve Rushen Phase 1 Wind Farm | wind farm | 5 | operational | 1.0 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.1979, -7.6365).