Molly Mountain (15 MW wind farm)

Molly Mountain is a 15 MW wind farm project in Fermanagh and Omagh, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 3 December 2014; the record was last updated on 19 March 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

15 MWwind farm
operationalstatus in REPD
19 March 2015record last updated
Fermanagh and Omaghcouncil area

Planning timeline

DateStage
15 August 2008Application submitted
1 February 2013Planning permission granted
30 March 2014Construction started
3 December 2014Operational

Project details

Technology
wind farm
Capacity
15 MW
Status (REPD)
operational
Record last updated
19 March 2015
Operator or applicant
Erne Concrete Pumping
Planning authority
Fermanagh and Omagh
Planning application reference
L/2008/1113/F
Turbines
5
Address (REPD)
Land at Molly Mountain near Derrylin
Council area (by location)
Fermanagh and Omagh
Time to decision
233 weeks
REPD reference
4066

Who decides

ApplicationsFermanagh and OmaghUK
Decided applications (solar, wind, battery)7410,236
Refused12 (16%)19%
Solar refused0 of 112%
Onshore wind refused12 of 7045%
Battery storage refused0 of 316%
Median time from submission to decision87.9 weeks17.0 weeks
Appeals lodged / allowed8 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Slieve Rushen Extensionwind farm54operational1.0
Slieve Rushen Phase 1 Wind Farmwind farm5operational1.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.1979, -7.6365).