Energy Projects Near You

Slieve Rushen Extension (54 MW wind farm)

Slieve Rushen Extension is a 54 MW wind farm project in Fermanagh and Omagh, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 April 2008; the record was last updated on 25 September 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

54 MWwind farm
operationalstatus in REPD
25 September 2014record last updated
Fermanagh and Omaghcouncil area

Planning timeline

DateStage
4 November 2004Application submitted
1 October 2006Planning permission granted
15 April 2008Operational

Project details

Technology
wind farm
Capacity
54 MW
Status (REPD)
operational
Record last updated
25 September 2014
Operator or applicant
Unknown
Planning authority
Fermanagh and Omagh
Planning application reference
L/2004/2058/F
Turbines
18
Address (REPD)
Slieve Rushen Derrylin Fermanagh
Council area (by location)
Fermanagh and Omagh
Time to decision
99 weeks
REPD reference
4504

Who decides

ApplicationsFermanagh and OmaghUK
Decided applications (solar, wind, battery)7410,236
Refused12 (16%)19%
Solar refused0 of 112%
Onshore wind refused12 of 7045%
Battery storage refused0 of 316%
Median time from submission to decision87.9 weeks17.0 weeks
Appeals lodged / allowed8 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Slieve Rushen Phase 1 Wind Farmwind farm5operational<0.1
Molly Mountainwind farm15operational1.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.1903, -7.6284).