Energy Projects Near You

Slieve Rushen Phase 1 Wind Farm (5 MW)

Slieve Rushen Phase 1 Wind Farm is a 5 MW wind farm project in Fermanagh and Omagh, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 December 1995; the record was last updated on 8 October 2013.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWwind farm
operationalstatus in REPD
8 October 2013record last updated
Fermanagh and Omaghcouncil area

Planning timeline

DateStage
15 May 1992Application submitted
2 November 1992Planning permission granted
1 December 1995Operational

Project details

Technology
wind farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
8 October 2013
Operator or applicant
Sean Quinn Group
Planning authority
Fermanagh and Omagh
Planning application reference
not recorded
Turbines
10
Address (REPD)
Slieve Rushen Derrylin 20km south of Enniskillen, County Fermanagh
Council area (by location)
Fermanagh and Omagh
Time to decision
24 weeks
REPD reference
3122

Who decides

ApplicationsFermanagh and OmaghUK
Decided applications (solar, wind, battery)7410,236
Refused12 (16%)19%
Solar refused0 of 112%
Onshore wind refused12 of 7045%
Battery storage refused0 of 316%
Median time from submission to decision87.9 weeks17.0 weeks
Appeals lodged / allowed8 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Slieve Rushen Extensionwind farm54operational<0.1
Molly Mountainwind farm15operational1.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.1903, -7.6284).