Wether Hill WindFarm (extension) (22 MW)

Wether Hill WindFarm (extension) is a 22 MW wind farm project in Dumfries and Galloway, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 20 February 2019; the record was last updated on 1 April 2019.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

22 MWwind farm
application withdrawnstatus in REPD
1 April 2019record last updated
Dumfries and Gallowaycouncil area

Planning timeline

DateStage
21 December 2015Application submitted
20 February 2019Application withdrawn

Project details

Technology
wind farm
Capacity
22 MW
Status (REPD)
application withdrawn
Record last updated
1 April 2019
Operator or applicant
Scottish Power Renewables
Planning authority
Dumfries and Galloway
Planning application reference
15/P/3/0502
Turbines
11
Turbine height
100 m
Address (REPD)
East and north of Wether Hill, Carsphairn, North west of Moniave, Castle Douglas
Council area (by location)
Dumfries and Galloway
REPD reference
4487

Who decides

ApplicationsDumfries and GallowayUK
Decided applications (solar, wind, battery)10610,236
Refused40 (38%)19%
Solar refused1 of 1812%
Onshore wind refused33 of 7245%
Battery storage refused6 of 1616%
Median time from submission to decision60.9 weeks17.0 weeks
Appeals lodged / allowed19 / 17—

Other large projects within 10 km

ProjectTypeMWStatuskm
Wether Hillwind farm18.2operational0.5
Longburn Wind Farmwind farm72application withdrawn1.0
Cornharrow Wind Farmwind farm38.4approved, not built3.9
Troston Loch Wind Farmbattery storage20approved, not built4.3
Troston Lochwind farm67.2approved, not built4.3
Lorg Windfarmwind farm64approved, not built6.6
Glenshimmeroch Wind Farmwind farm36approved, not built7.6
Margree Windfarmwind farm49.9approved, not built8.0
Shepherd's Rig Wind Farmwind farm81approved, not built8.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.2226, -4.0373).