Wether Hill (18.2 MW wind farm)

Wether Hill is an 18.2 MW wind farm project in Dumfries and Galloway, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 May 2007; the record was last updated on 25 September 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

18.2 MWwind farm
operationalstatus in REPD
25 September 2014record last updated
Dumfries and Gallowaycouncil area

Planning timeline

DateStage
8 January 2004Application submitted
1 March 2005Planning permission granted
1 August 2006Construction started
1 May 2007Operational

Project details

Technology
wind farm
Capacity
18.2 MW
Status (REPD)
operational
Record last updated
25 September 2014
Operator or applicant
Scottish Power/CRE Energy
Planning authority
Dumfries and Galloway
Planning application reference
03P30746
Turbines
14
Address (REPD)
Moniaive Dumfries
Council area (by location)
Dumfries and Galloway
Time to decision
60 weeks
REPD reference
4519

Who decides

ApplicationsDumfries and GallowayUK
Decided applications (solar, wind, battery)10610,236
Refused40 (38%)19%
Solar refused1 of 1812%
Onshore wind refused33 of 7245%
Battery storage refused6 of 1616%
Median time from submission to decision60.9 weeks17.0 weeks
Appeals lodged / allowed19 / 17—

Other large projects within 10 km

ProjectTypeMWStatuskm
Wether Hill WindFarm (extension)wind farm22application withdrawn0.5
Longburn Wind Farmwind farm72application withdrawn0.8
Cornharrow Wind Farmwind farm38.4approved, not built3.5
Troston Loch Wind Farmbattery storage20approved, not built4.2
Troston Lochwind farm67.2approved, not built4.2
Lorg Windfarmwind farm64approved, not built6.4
Glenshimmeroch Wind Farmwind farm36approved, not built7.4
Shepherd's Rig Wind Farmwind farm81approved, not built7.7
Margree Windfarmwind farm49.9approved, not built7.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.2231, -4.0452).