Solar, wind and battery projects near Oldham (OL4)
47 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of OL4 (Oldham): 4 are waiting for a planning decision, 37 approved but not yet running, 2 operational. The largest live scheme is Printworks Road - Stalybridge Battery Storage (150 MW battery storage, approved on 15 December 2023, not yet built), 5.7 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of OL4
Projects of 1 MW and more (17)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Lowerfields Farm, Warren Lanebattery storage | battery storage | 27 | application submittedupdated Sep 2025 | Jul 2025 | — | Sep 2025 | Oldham | 1.9 |
| Chaddertonbattery storage | battery storage | 2.5 | approved, not built may be out of dateupdated Mar 2022 | Mar 2022 | granted May 2022 | Mar 2022 | Oldham | 4.3 |
| IGC, Lydia Becker Wayrooftop solar | rooftop solar | 3.1 | approved, not builtupdated Sep 2025 | Aug 2025 | granted Sep 2025 | Sep 2025 | Oldham | 5.0 |
| Printworks Road - Stalybridge Battery Storagebattery storage | battery storage | 150 | approved, not builtupdated Dec 2023 | Sep 2023 | granted Dec 2023 | Dec 2023 | Tameside | 5.7 |
| Denshaw Windfarmwind farm | wind farm | 10.5 | refusedupdated Sep 2005 | Dec 2003 | refused Feb 2006 | Sep 2005 | Oldham | 5.9 |
| Whitegate Battery Storagebattery storage | battery storage | 57 | under constructionupdated Oct 2025 | Feb 2022 | granted May 2022 | Oct 2025 | Oldham | 6.2 |
| Chaddertonbattery storage | battery storage | 20 | under constructionupdated May 2022 | Apr 2022 | granted Dec 2022 | May 2022 | Oldham | 6.2 |
| Holden Waybattery storage | battery storage | 6 | approved, not built may be out of dateupdated Jun 2020 | Apr 2017 | granted Jun 2018 | Jun 2020 | Tameside | 6.7 |
| Ellenroad Farm, Bentgate Streetbattery storage | battery storage | 30 | approved, not builtupdated Jun 2025 | Oct 2024 | granted Mar 2025 | Jun 2025 | Rochdale | 6.8 |
| Medlock Road, Failsworthbattery storage | battery storage | 30 | approved, not builtupdated Nov 2025 | Oct 2024 | granted Oct 2025 | Nov 2025 | Oldham | 7.0 |
| Tesco Distribution Centre, Stakehill Industrial Estaterooftop solar | rooftop solar | 1 | approved, not builtupdated Apr 2024 | Feb 2024 | granted Apr 2024 | Apr 2024 | Rochdale | 7.0 |
| Robert McBride Ltdrooftop solar | rooftop solar | 1.3 | permission expiredupdated Aug 2018 | Mar 2015 | granted Apr 2015 | Aug 2018 | Rochdale | 8.5 |
| Miall Power Energy Storage Facilitybattery storage | battery storage | 5 | refusedupdated Apr 2021 | Feb 2021 | refused Jun 2021 | Apr 2021 | Rochdale | 9.2 |
| Astra Centre, Royal Barn Roadbattery storage | battery storage | 40 | under constructionupdated Feb 2024 | Sep 2021 | granted Nov 2021 | Feb 2024 | Rochdale | 9.2 |
| Gipsy Lanebattery storage | battery storage | 20 | under constructionupdated Jul 2021 | Nov 2019 | granted Mar 2020 | Jul 2021 | Rochdale | 9.3 |
| Godley Water Treatment Worksfloating solar | floating solar | 3 | operationalupdated Jun 2016 | — | — | Jun 2016 | Tameside | 9.8 |
| Moston Valebattery storage | battery storage | 10 | under constructionupdated May 2021 | Jul 2020 | granted Nov 2020 | May 2021 | Manchester | 9.8 |
Smaller schemes under 1 MW, mostly rooftop solar (30)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Molnlycke Healthcare, Brook Streetrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Apr 2023 | Feb 2023 | granted Mar 2023 | Apr 2023 | Oldham | 1.8 |
| Sainsburys Supermarkets, Union Streetrooftop solar | rooftop solar | 0.4 | approved, not builtupdated May 2026 | Feb 2026 | granted Apr 2026 | May 2026 | Oldham | 2.5 |
| Tesco Stores, Featherstall Road Northrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Aug 2023 | Jun 2023 | granted Jul 2023 | Aug 2023 | Oldham | 3.5 |
| Featherstall Road Tesco (Chadderton)rooftop solar | rooftop solar | 0.5 | approved, not builtupdated Mar 2020 | Jan 2020 | granted Mar 2020 | Mar 2020 | Oldham | 3.5 |
| Oldham Athletic Football Club, Hilbre Avenuerooftop solar | rooftop solar | 0.4 | approved, not builtupdated Nov 2025 | Sep 2025 | granted Oct 2025 | Nov 2025 | Oldham | 3.8 |
| Bentfield Industrial Unitsbattery storage | battery storage | 0.3 | approved, not built may be out of dateupdated Jan 2021 | Feb 2020 | granted May 2020 | Jan 2021 | Oldham | 4.1 |
| Manor Mill, Victoria Streetrooftop solar | rooftop solar | 0.5 | approved, not built may be out of dateupdated Dec 2022 | Aug 2022 | granted Dec 2022 | Dec 2022 | Oldham | 4.2 |
| Tameside General Hospital, Fountain Streetrooftop solar | rooftop solar | 0.3 | application submitted | Jun 2026 | — | — | Tameside | 5.7 |
| Middleton Associates, Chaddertonrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Oct 2023 | Sep 2023 | granted Oct 2023 | Oct 2023 | Oldham | 5.7 |
| Tameside College, Beaufort Roadrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Sep 2025 | Jul 2025 | granted Sep 2025 | Sep 2025 | Tameside | 6.1 |
| Land at Wrigley Headsolar farm | solar farm | 0.9 | under constructionupdated Mar 2026 | Mar 2020 | granted Dec 2021 | Mar 2026 | Manchester | 6.1 |
| Airtech Advanced Materialsrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Nov 2025 | Sep 2025 | granted Oct 2025 | Nov 2025 | Oldham | 6.1 |
| Foxdenton Lane, Chaddertonrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jan 2025 | Dec 2024 | granted Jan 2025 | Jan 2025 | Oldham | 6.2 |
| Oldham Broadway Business Park, Broadgaterooftop solar | rooftop solar | 0.2 | approved, not builtupdated Apr 2024 | Dec 2023 | granted Mar 2024 | Apr 2024 | Oldham | 6.4 |
| Oldham Broadway Business Park Solar Panelsrooftop solar | rooftop solar | — | approved, not builtupdated Mar 2021 | Feb 2021 | granted Apr 2021 | Mar 2021 | Oldham | 6.4 |
| Laurus Ryecroft High School, Lumb Lanerooftop solar | rooftop solar | 0.3 | approved, not builtupdated Sep 2025 | Jul 2025 | granted Sep 2025 | Sep 2025 | Tameside | 6.6 |
| Burlington Streetrooftop solar | rooftop solar | 0.9 | approved, not builtupdated Jan 2024 | Nov 2023 | granted Jan 2024 | Jan 2024 | Tameside | 6.7 |
| Dig Gate Lanebattery storage | battery storage | — | approved, not builtupdated May 2025 | Feb 2024 | granted Apr 2025 | May 2025 | Rochdale | 6.9 |
| Tame Box, Tame Streetbattery storage | battery storage | 0.2 | approved, not built may be out of dateupdated Nov 2022 | Sep 2022 | granted Oct 2022 | Nov 2022 | Tameside | 7.0 |
| Cardinal Langley RC High School, Rochdale Roadrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Nov 2025 | Jul 2025 | granted Sep 2025 | Nov 2025 | Rochdale | 7.7 |
| The West Side Of Hanson Street, Middletonbattery storage | battery storage | 0.2 | application submitted may be out of dateupdated Feb 2023 | Feb 2023 | — | Feb 2023 | Rochdale | 7.8 |
| Hopwood Hall College, Rochdale Roadrooftop solar | rooftop solar | 0.5 | application submittedupdated Sep 2024 | Aug 2024 | — | Sep 2024 | Rochdale | 8.2 |
| Tudor Industrial Estate, Ashton Street- Micro Energy Storagebattery storage | battery storage | 0.2 | approved, not builtupdated Oct 2025 | Jun 2025 | granted Sep 2025 | Oct 2025 | Tameside | 8.3 |
| Reliance Trading Estate,Reliance Streetrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Aug 2023 | Jun 2023 | granted Aug 2023 | Aug 2023 | Manchester | 8.3 |
| Inkech, Crawford Streetrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jul 2025 | May 2025 | granted Jul 2025 | Jul 2025 | Rochdale | 8.6 |
| The Sharp Projectrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jun 2021 | Jun 2021 | granted Aug 2021 | Jun 2021 | Manchester | 9.3 |
| Concordiarooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jan 2024 | Nov 2023 | granted Jan 2024 | Jan 2024 | Tameside | 9.3 |
| Gipsy Lane Battery Energy Storage Facilitybattery storage | battery storage | — | application withdrawnupdated Jan 2019 | Oct 2018 | — | Jan 2019 | Rochdale | 9.3 |
| Sheffield Roadbattery storage | battery storage | — | approved, not built may be out of dateupdated Mar 2022 | Feb 2022 | granted Sep 2022 | Mar 2022 | Tameside | 9.5 |
| Central Park Solar photovalticsrooftop solar | rooftop solar | 0.1 | operationalupdated Jul 2021 | Jun 2021 | granted Sep 2021 | Jul 2021 | Manchester | 9.6 |
Distance from the average position of the OL4 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 1 | 0 | 1 | 0 | 0 | 0.9 |
| Rooftop solar | 25 | 2 | 21 | 1 | 0 | 11.6 |
| Floating solar | 1 | 0 | 0 | 1 | 0 | 0 |
| Wind farm | 1 | 0 | 0 | 0 | 1 | 0 |
| Battery storage | 19 | 2 | 15 | 0 | 1 | 393 |
MW in pipeline: pending, approved and under-construction capacity.
How Oldham decides solar, wind and battery applications
| Applications | Oldham | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 19 | 10,236 |
| Refused | 2 (11%) | 19% |
| Solar refused | 0 of 13 | 12% |
| Onshore wind refused | 1 of 1 | 45% |
| Battery storage refused | 1 of 5 | 16% |
| Median time from submission to decision | 9.0 weeks | 17.0 weeks |
| Appeals lodged / allowed | 1 / 1 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near OL4, 7 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.