Hunters Race Solar Park (9.3 MW)

Hunters Race Solar Park is a 9.3 MW solar farm project in Chichester, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 23 July 2014; the record was last updated on 2 October 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

9.3 MWsolar farm
operationalstatus in REPD
2 October 2014record last updated
Chichestercouncil area

Planning timeline

DateStage
12 February 2013Application submitted
13 May 2013Planning permission granted
12 March 2014Construction started
23 July 2014Operational

Project details

Technology
solar farm
Capacity
9.3 MW
Status (REPD)
operational
Record last updated
2 October 2014
Operator or applicant
Aardvark Environment Matters
Planning authority
Chichester
Planning application reference
13/00382/FUL
Site area
12.4 ha
Address (REPD)
Lavant Quarry, Hunters Race, Lavant, Chichester, West Sussex
Council area (by location)
Chichester
Time to decision
13 weeks
REPD reference
2280

Who decides

ApplicationsChichesterUK
Decided applications (solar, wind, battery)2510,236
Refused4 (16%)19%
Solar refused4 of 2412%
Battery storage refused0 of 116%
Median time from submission to decision12.9 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Former Westhampnett Landfillsolar farm7.5operational3.8
Strettington Solar Farmsolar farm5operational4.5
Merston Solar Parksolar farm10operational6.5
Land at Tangmere Airfieldsolar farm5operational6.6
Oving Solar Farmsolar farm5operational6.7
Boxgrove Common, Tinwood Lanebattery storage70approved, not built7.4
Mundham, Runcton Lane Solar Farmsolar farm30approved, not built7.5
Decoy Farm House Solar Modulessolar farm6operational8.0
Park Farmsolar farm5operational8.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.8621, -0.7927).