Energy Projects Near You

Solar, wind and battery projects near Manchester (M15)

111 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of M15 (Manchester): 5 are waiting for a planning decision, 87 approved but not yet running, 9 operational. The largest live scheme is Daines Battery Energy Storage System (600 MW battery storage, approved on 15 May 2025, not yet built), 9.8 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

111projects within 10 km
5awaiting a decision
87approved, not running
9operational

Projects within 10 km of M15

Projects of 1 MW and more (21)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
City of Manchester Stadiumwind turbinewind turbine2abandonedupdated Nov 2008Sep 2005granted Sep 2006Nov 2008Manchester3.9
City Football Academy, Ashton New Roadrooftop solarrooftop solar3.4operationalupdated Jun 2026Mar 2024granted Apr 2024Jun 2026Manchester4.1
City Football Academysolar farmsolar farm1.1approved, not builtupdated Jan 2025Oct 2024granted Dec 2024Jan 2025Manchester4.1
Moston Valebattery storagebattery storage10under constructionupdated May 2021Jul 2020granted Nov 2020May 2021Manchester5.1
Golf Roadbattery storagebattery storage90approved, not builtupdated Oct 2024Jun 2023granted Oct 2024Oct 2024Trafford5.5
Sale Golf Club, Golf Roadbattery storagebattery storage70approved, not builtupdated Nov 2023Apr 2023granted Nov 2023Nov 2023Trafford5.5
Freshfields, Fairy Lanebattery storagebattery storage99.9under constructionupdated Jan 2026Oct 2022granted Mar 2023Jan 2026Trafford5.7
West Didsbury Battery Storagebattery storagebattery storage50operationalupdated Nov 2023Sep 2017granted Nov 2019Nov 2023Trafford5.8
Tesco Burnage Storerooftop solarrooftop solar1approved, not builtupdated Jun 2020Nov 2019granted Jan 2020Jun 2020Manchester6.0
Tesco Store East Didsburyrooftop solarrooftop solar1approved, not builtupdated Feb 2021Nov 2019granted Jan 2020Feb 2021Manchester6.5
Medlock Road, Failsworthbattery storagebattery storage30approved, not builtupdated Nov 2025Oct 2024granted Oct 2025Nov 2025Oldham7.7
Denton Hall Farm Road, Dentonrooftop solarrooftop solar1.2operationalupdated Jan 2022Jan 2022granted Jul 2023Jan 2022Tameside8.1
Wild Fowl Farm, Carrington Lanebattery storagebattery storage35approved, not builtupdated Mar 2025May 2024refused Aug 2024Mar 2025Trafford8.7
Chaddertonbattery storagebattery storage20under constructionupdated May 2022Apr 2022granted Dec 2022May 2022Oldham9.0
Whitegate Battery Storagebattery storagebattery storage57under constructionupdated Oct 2025Feb 2022granted May 2022Oct 2025Oldham9.1
Robert McBride Ltdrooftop solarrooftop solar1.3permission expiredupdated Aug 2018Mar 2015granted Apr 2015Aug 2018Rochdale9.4
Welkin Mill, Welkin Roadbattery storagebattery storage49.9under constructionupdated Apr 2024Dec 2022granted Aug 2023Apr 2024Stockport9.5
Welkin Road, Bredburybattery storagebattery storage20operationalupdated Jan 2026Dec 2020granted Jan 2021Jan 2026Stockport9.6
Daines Battery Energy Storage Systembattery storagebattery storage600approved, not builtupdated Jun 2025Oct 2024granted May 2025Jun 2025Trafford9.8
Bredbury Substationbattery storagebattery storage49.9under constructionupdated Sep 2021Sep 2021granted Dec 2021Sep 2021Stockport9.8
Ashton Road, Bredburybattery storagebattery storage75approved, not builtupdated Aug 2025Jan 2025granted Jul 2025Aug 2025Stockport9.9
Smaller schemes under 1 MW, mostly rooftop solar (60)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Manchester Metropolitan University, Birley Fieldsrooftop solarrooftop solar0.2approved, not builtupdated Aug 2023Jun 2023granted Aug 2023Aug 2023Manchester0.2
Loreto College, Chichester Roadrooftop solarrooftop solar0.4approved, not builtupdated Nov 2025Aug 2025granted Oct 2025Nov 2025Manchester0.7
Royal Northern College Of Music, Oxford Roadrooftop solarrooftop solar0.2under constructionupdated Sep 2021Aug 2021granted Jul 2022Sep 2021Manchester1.0
Ymca And Castlefield Hotel, Liverpool Roadrooftop solarrooftop solar0.2application withdrawnupdated Feb 2024Dec 2023—Feb 2024Manchester1.0
The Windrush Millenium Centre, Alexandra Roadrooftop solarrooftop solar—approved, not builtupdated Jan 2026Oct 2025granted Dec 2025Jan 2026Manchester1.3
Manchester Marriott Victoria And Albert Hotelrooftop solarrooftop solar0.2abandonedupdated Jul 2024Dec 2023granted Jun 2024Jul 2024Salford1.4
Sainsburys Supermarket, Regent Roadrooftop solarrooftop solar0.3approved, not builtupdated Nov 2025Aug 2025granted Sep 2025Nov 2025Salford1.5
Manchester Academy, Moss Lane Eastrooftop solarrooftop solar—approved, not builtupdated Aug 2023Jul 2023granted Aug 2023Aug 2023Manchester1.6
Manchester Academy, Moss Lane Eastrooftop solarrooftop solar0.2approved, not builtupdated Jan 2026Nov 2025granted Dec 2025Jan 2026Manchester1.6
Manchester Royal Infirmary, Oxford Roadrooftop solarrooftop solar—approved, not builtupdated Apr 2026Dec 2025granted Feb 2026Apr 2026Manchester1.7
The Printworks, Withy Groverooftop solarrooftop solar0.2approved, not builtupdated Aug 2025Jun 2025granted Aug 2025Aug 2025Manchester2.1
Brunel Avenuerooftop solarrooftop solar0.2application submittedupdated Feb 2026Jan 2026—Feb 2026Salford2.2
Xaverian College, Lower Park Roadrooftop solarrooftop solar0.2approved, not builtupdated Apr 2024Mar 2023granted Apr 2024Apr 2024Manchester2.4
Metrolink Trafford Depot, Warwick Road Solar Arraysrooftop solarrooftop solar0.3approved, not builtupdated Feb 2022Jan 2022granted Mar 2022Feb 2022Trafford2.6
Metrolink Trafford Depot Solar Panels & Battery Storagerooftop solarrooftop solar0.3refusedupdated Dec 2021May 2021refused Jul 2021Dec 2021Trafford2.6
Metrolink Trafford Depot Solar Panels & Battery Storagebattery storagebattery storage—refusedupdated Dec 2021May 2021refused Jul 2021Dec 2021Trafford2.6
Whalley Range High School, Wilbraham Roadrooftop solarrooftop solar0.4approved, not builtupdated Oct 2025Aug 2025granted Sep 2025Oct 2025Manchester2.8
Outer Space Studios Solar Panelsrooftop solarrooftop solar0.6operationalupdated Jan 2022Jun 2021granted Nov 2021Jan 2022Manchester3.5
The Albion Academy, London Streetrooftop solarrooftop solar0.2approved, not builtupdated Nov 2025Aug 2025granted Oct 2025Nov 2025Salford3.5
Longford Park School, Cromwell Roadrooftop solarrooftop solar0.4approved, not builtupdated Dec 2022Nov 2022granted Dec 2022Dec 2022Trafford3.6
Riverside Works, Collyhurst Roadrooftop solarrooftop solar0.5approved, not builtupdated Apr 2026Jan 2026granted Feb 2026Apr 2026Manchester3.7
Etihad Stadium, Ashton New Roadrooftop solarrooftop solar0.2approved, not builtupdated May 2025Mar 2025granted May 2025May 2025Manchester3.7
Gamma Telecom, Second Avenuerooftop solarrooftop solar0.2approved, not builtupdated Dec 2025Jul 2025granted Sep 2025Dec 2025Trafford3.8
East Manchester Academy, Grey Mare Lanerooftop solarrooftop solar0.2approved, not builtupdated Sep 2025Aug 2025granted Sep 2025Sep 2025Manchester3.8
Duo Plastics Limited, Vickers Streetrooftop solarrooftop solar0.6application submittedupdated Nov 2024Sep 2024—Nov 2024Manchester4.0
Fifth Avenue, Trafford Parkrooftop solarrooftop solar0.3approved, not builtupdated Jun 2022May 2022granted Jul 2022Jun 2022Trafford4.1
CHEP Manchester, Trafford Parkrooftop solarrooftop solar0.3approved, not builtupdated May 2024Mar 2024granted Apr 2024May 2024Trafford4.1
Pisces, Mosley Road, Unit Brooftop solarrooftop solar0.2approved, not builtupdated Mar 2026Dec 2025granted Feb 2026Mar 2026Trafford4.2
Ashton Old Roadrooftop solarrooftop solar0.4approved, not builtupdated May 2022Apr 2022granted Jun 2022May 2022Manchester4.2
Co Op Academy Belle Vue, Hyde Roadrooftop solarrooftop solar0.2approved, not builtupdated Apr 2026Jan 2026granted Feb 2026Apr 2026Manchester4.2
Broughton Hub, Rigby Streetrooftop solarrooftop solar0.2approved, not builtupdated Nov 2024Sep 2024granted Nov 2024Nov 2024Salford4.4
The National Cycling Centre Velodromerooftop solarrooftop solar0.7operationalupdated Mar 2023Sep 2020granted Oct 2020Mar 2023Manchester4.4
DB Schenker, Mosley Road Solar Arraysrooftop solarrooftop solar0.2approved, not builtupdated Oct 2023Aug 2023granted Oct 2023Oct 2023Trafford4.4
Turnpike Depotsolar farmsolar farm0.5under constructionupdated May 2023May 2023—May 2023Salford4.5
Unit C, Kelbrook Roadrooftop solarrooftop solar0.6approved, not builtupdated Sep 2023Jul 2023granted Aug 2023Sep 2023Manchester4.5
The National Cycling Centrerooftop solarrooftop solar0.9under constructionupdated Apr 2022Apr 2022granted Aug 2022Apr 2022Manchester4.5
G H Sheldon, Stainburn Roadrooftop solarrooftop solar0.3approved, not builtupdated Jul 2023May 2023granted Jul 2023Jul 2023Manchester4.5
Manchester Communication Academy, Silchester Driverooftop solarrooftop solar0.3approved, not builtupdated Sep 2023Aug 2023granted Sep 2023Sep 2023Manchester4.5
Central Park Estate, Trafford Park, Unit 22,rooftop solarrooftop solar0.5approved, not builtupdated May 2026Jan 2026granted Mar 2026May 2026Trafford4.6
Hammerstone Road Depotrooftop solarrooftop solar—approved, not builtupdated Nov 2023Sep 2023granted Nov 2023Nov 2023Manchester4.8
New Smithfield Market, Whitworth Street East -Solar Panelsrooftop solarrooftop solar0.3approved, not builtupdated Jan 2025Oct 2024granted Dec 2024Jan 2025Manchester5.0
New Smithfield Marketrooftop solarrooftop solar0.2approved, not builtupdated Jan 2025Oct 2024granted Dec 2024Jan 2025Manchester5.0
Central Park Solar photovalticsrooftop solarrooftop solar0.1operationalupdated Jul 2021Jun 2021granted Sep 2021Jul 2021Manchester5.1
Tesco Super-Store (Garratt Way, Gorton)rooftop solarrooftop solar0.7operationalupdated Jul 2020Jan 2019granted Mar 2019Jul 2020Manchester5.2
Bowless Exhibition, Longeridge Road Solar Panels Arrayrooftop solarrooftop solar1approved, not builtupdated Jan 2026Oct 2025granted Dec 2025Jan 2026Trafford5.2
The Sharp Projectrooftop solarrooftop solar0.3approved, not builtupdated Jun 2021Jun 2021granted Aug 2021Jun 2021Manchester5.3
Jj Food Service, 1A Lamplight Wayrooftop solarrooftop solar0.4approved, not builtupdated Nov 2023Aug 2023granted Nov 2023Nov 2023Salford5.3
Gorton Education Village, Wembley Roadrooftop solarrooftop solar0.6approved, not builtupdated Dec 2025Oct 2025granted Nov 2025Dec 2025Manchester5.4
Lostock High Schoolrooftop solarrooftop solar0.2refusedupdated Dec 2025Aug 2025refused Oct 2025Dec 2025Trafford5.5
Barton Dock Road, Trafford Parkrooftop solarrooftop solar0.3refusedupdated Dec 2025Sep 2025refused Oct 2025Dec 2025Trafford5.9
Reliance Trading Estate,Reliance Streetrooftop solarrooftop solar0.4approved, not builtupdated Aug 2023Jun 2023granted Aug 2023Aug 2023Manchester6.2
Springfield Primary School, Springfield Road Solar Panels Arrayrooftop solarrooftop solar0.2approved, not builtupdated Dec 2025Jul 2025granted Sep 2025Dec 2025Trafford6.7
Scotscroft Towers Business Park, Wilmslow Roadrooftop solarrooftop solar0.1approved, not built may be out of dateupdated Feb 2024Jan 2024granted Feb 2024Feb 2024Manchester6.7
City Of Salford Highway Services, Swinton Hall Roadrooftop solarrooftop solar0.2approved, not built may be out of dateupdated May 2023May 2023granted Jul 2023May 2023Salford7.0
Barton Business Park, Cawdor Streetrooftop solarrooftop solar0.2approved, not builtupdated Jun 2026Mar 2026granted May 2026Jun 2026Salford7.0
Golden Way, Urmston - Unit 24 - Solar Panelsrooftop solarrooftop solar0.4approved, not builtupdated Oct 2024Jul 2024granted Sep 2024Oct 2024Trafford7.1
David Lloyd Manchester, Barton Embankmentrooftop solarrooftop solar0.2approved, not builtupdated Apr 2024Jan 2024granted Mar 2024Apr 2024Trafford7.2
Herrod Avenue, South Reddishbattery storagebattery storage—application withdrawnupdated Jun 2024Dec 2023—Jun 2024Stockport7.4
Polyflor Limited, Prestwich Delivery Officerooftop solarrooftop solar—approved, not builtupdated Jul 2025Apr 2025granted Jul 2025Jul 2025Bury7.8
Dixons Brooklands Academy, Moor Roadrooftop solarrooftop solar0.2approved, not builtupdated Sep 2025Jul 2025granted Sep 2025Sep 2025Manchester7.9

30 more projects not listed (furthest or smallest).

Distance from the average position of the M15 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm303002.5
Rooftop solar883717323.5
Wind turbine100000
Battery storage19213211,187

MW in pipeline: pending, approved and under-construction capacity.

How Manchester decides solar, wind and battery applications

ApplicationsManchesterUK
Decided applications (solar, wind, battery)5010,236
Refused4 (8%)19%
Solar refused4 of 4812%
Onshore wind refused0 of 145%
Battery storage refused0 of 116%
Median time from submission to decision7.6 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

All projects in Manchester

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near M15, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.