Energy Projects Near You

Solar, wind and battery projects near Manchester (M12)

112 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of M12 (Manchester): 6 are waiting for a planning decision, 87 approved but not yet running, 10 operational. The largest live scheme is Freshfields, Fairy Lane (99.9 MW battery storage, under construction since 1 January 2026), 7.3 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

112projects within 10 km
6awaiting a decision
87approved, not running
10operational

Projects within 10 km of M12

Projects of 1 MW and more (24)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
City Football Academy, Ashton New Roadrooftop solarrooftop solar3.4operationalupdated Jun 2026Mar 2024granted Apr 2024Jun 2026Manchester2.0
City Football Academysolar farmsolar farm1.1approved, not builtupdated Jan 2025Oct 2024granted Dec 2024Jan 2025Manchester2.0
City of Manchester Stadiumwind turbinewind turbine2abandonedupdated Nov 2008Sep 2005granted Sep 2006Nov 2008Manchester2.5
Moston Valebattery storagebattery storage10under constructionupdated May 2021Jul 2020granted Nov 2020May 2021Manchester4.6
Denton Hall Farm Road, Dentonrooftop solarrooftop solar1.2operationalupdated Jan 2022Jan 2022granted Jul 2023Jan 2022Tameside4.8
Tesco Burnage Storerooftop solarrooftop solar1approved, not builtupdated Jun 2020Nov 2019granted Jan 2020Jun 2020Manchester5.0
Medlock Road, Failsworthbattery storagebattery storage30approved, not builtupdated Nov 2025Oct 2024granted Oct 2025Nov 2025Oldham5.1
Tesco Store East Didsburyrooftop solarrooftop solar1approved, not builtupdated Feb 2021Nov 2019granted Jan 2020Feb 2021Manchester5.9
Welkin Mill, Welkin Roadbattery storagebattery storage49.9under constructionupdated Apr 2024Dec 2022granted Aug 2023Apr 2024Stockport6.8
Ashton Road, Bredburybattery storagebattery storage75approved, not builtupdated Aug 2025Jan 2025granted Jul 2025Aug 2025Stockport6.9
Welkin Road, Bredburybattery storagebattery storage20operationalupdated Jan 2026Dec 2020granted Jan 2021Jan 2026Stockport6.9
Bredbury Substationbattery storagebattery storage49.9under constructionupdated Sep 2021Sep 2021granted Dec 2021Sep 2021Stockport7.2
Freshfields, Fairy Lanebattery storagebattery storage99.9under constructionupdated Jan 2026Oct 2022granted Mar 2023Jan 2026Trafford7.3
West Didsbury Battery Storagebattery storagebattery storage50operationalupdated Nov 2023Sep 2017granted Nov 2019Nov 2023Trafford7.3
Golf Roadbattery storagebattery storage90approved, not builtupdated Oct 2024Jun 2023granted Oct 2024Oct 2024Trafford7.4
Sale Golf Club, Golf Roadbattery storagebattery storage70approved, not builtupdated Nov 2023Apr 2023granted Nov 2023Nov 2023Trafford7.4
Chaddertonbattery storagebattery storage20under constructionupdated May 2022Apr 2022granted Dec 2022May 2022Oldham7.8
Whitegate Battery Storagebattery storagebattery storage57under constructionupdated Oct 2025Feb 2022granted May 2022Oct 2025Oldham7.9
Goyt Hall Farm, Goyt Valley Footpathbattery storagebattery storage40approved, not builtupdated Sep 2024Dec 2023granted Aug 2024Sep 2024Stockport8.4
Holden Waybattery storagebattery storage6approved, not built may be out of dateupdated Jun 2020Apr 2017granted Jun 2018Jun 2020Tameside8.4
Robert McBride Ltdrooftop solarrooftop solar1.3permission expiredupdated Aug 2018Mar 2015granted Apr 2015Aug 2018Rochdale9.2
IGC, Lydia Becker Wayrooftop solarrooftop solar3.1approved, not builtupdated Sep 2025Aug 2025granted Sep 2025Sep 2025Oldham9.3
Godley Water Treatment Worksfloating solarfloating solar3operationalupdated Jun 2016——Jun 2016Tameside9.6
Chaddertonbattery storagebattery storage2.5approved, not built may be out of dateupdated Mar 2022Mar 2022granted May 2022Mar 2022Oldham9.6
Smaller schemes under 1 MW, mostly rooftop solar (60)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Outer Space Studios Solar Panelsrooftop solarrooftop solar0.6operationalupdated Jan 2022Jun 2021granted Nov 2021Jan 2022Manchester0.6
Co Op Academy Belle Vue, Hyde Roadrooftop solarrooftop solar0.2approved, not builtupdated Apr 2026Jan 2026granted Feb 2026Apr 2026Manchester0.9
Ashton Old Roadrooftop solarrooftop solar0.4approved, not builtupdated May 2022Apr 2022granted Jun 2022May 2022Manchester1.3
East Manchester Academy, Grey Mare Lanerooftop solarrooftop solar0.2approved, not builtupdated Sep 2025Aug 2025granted Sep 2025Sep 2025Manchester1.5
Hammerstone Road Depotrooftop solarrooftop solar—approved, not builtupdated Nov 2023Sep 2023granted Nov 2023Nov 2023Manchester1.6
Unit C, Kelbrook Roadrooftop solarrooftop solar0.6approved, not builtupdated Sep 2023Jul 2023granted Aug 2023Sep 2023Manchester1.7
Xaverian College, Lower Park Roadrooftop solarrooftop solar0.2approved, not builtupdated Apr 2024Mar 2023granted Apr 2024Apr 2024Manchester1.7
Manchester Royal Infirmary, Oxford Roadrooftop solarrooftop solar—approved, not builtupdated Apr 2026Dec 2025granted Feb 2026Apr 2026Manchester1.7
G H Sheldon, Stainburn Roadrooftop solarrooftop solar0.3approved, not builtupdated Jul 2023May 2023granted Jul 2023Jul 2023Manchester1.8
Tesco Super-Store (Garratt Way, Gorton)rooftop solarrooftop solar0.7operationalupdated Jul 2020Jan 2019granted Mar 2019Jul 2020Manchester1.9
New Smithfield Market, Whitworth Street East -Solar Panelsrooftop solarrooftop solar0.3approved, not builtupdated Jan 2025Oct 2024granted Dec 2024Jan 2025Manchester1.9
New Smithfield Marketrooftop solarrooftop solar0.2approved, not builtupdated Jan 2025Oct 2024granted Dec 2024Jan 2025Manchester1.9
Etihad Stadium, Ashton New Roadrooftop solarrooftop solar0.2approved, not builtupdated May 2025Mar 2025granted May 2025May 2025Manchester2.2
Manchester Academy, Moss Lane Eastrooftop solarrooftop solar0.2approved, not builtupdated Jan 2026Nov 2025granted Dec 2025Jan 2026Manchester2.3
Manchester Academy, Moss Lane Eastrooftop solarrooftop solar—approved, not builtupdated Aug 2023Jul 2023granted Aug 2023Aug 2023Manchester2.3
Gorton Education Village, Wembley Roadrooftop solarrooftop solar0.6approved, not builtupdated Dec 2025Oct 2025granted Nov 2025Dec 2025Manchester2.4
Royal Northern College Of Music, Oxford Roadrooftop solarrooftop solar0.2under constructionupdated Sep 2021Aug 2021granted Jul 2022Sep 2021Manchester2.4
The National Cycling Centre Velodromerooftop solarrooftop solar0.7operationalupdated Mar 2023Sep 2020granted Oct 2020Mar 2023Manchester2.4
The National Cycling Centrerooftop solarrooftop solar0.9under constructionupdated Apr 2022Apr 2022granted Aug 2022Apr 2022Manchester2.4
Manchester Metropolitan University, Birley Fieldsrooftop solarrooftop solar0.2approved, not builtupdated Aug 2023Jun 2023granted Aug 2023Aug 2023Manchester3.1
Duo Plastics Limited, Vickers Streetrooftop solarrooftop solar0.6application submittedupdated Nov 2024Sep 2024—Nov 2024Manchester3.2
Loreto College, Chichester Roadrooftop solarrooftop solar0.4approved, not builtupdated Nov 2025Aug 2025granted Oct 2025Nov 2025Manchester3.4
The Printworks, Withy Groverooftop solarrooftop solar0.2approved, not builtupdated Aug 2025Jun 2025granted Aug 2025Aug 2025Manchester3.5
The Windrush Millenium Centre, Alexandra Roadrooftop solarrooftop solar—approved, not builtupdated Jan 2026Oct 2025granted Dec 2025Jan 2026Manchester3.5
Whalley Range High School, Wilbraham Roadrooftop solarrooftop solar0.4approved, not builtupdated Oct 2025Aug 2025granted Sep 2025Oct 2025Manchester3.8
Ymca And Castlefield Hotel, Liverpool Roadrooftop solarrooftop solar0.2application withdrawnupdated Feb 2024Dec 2023—Feb 2024Manchester3.9
Manchester Marriott Victoria And Albert Hotelrooftop solarrooftop solar0.2abandonedupdated Jul 2024Dec 2023granted Jun 2024Jul 2024Salford4.0
Riverside Works, Collyhurst Roadrooftop solarrooftop solar0.5approved, not builtupdated Apr 2026Jan 2026granted Feb 2026Apr 2026Manchester4.0
The Sharp Projectrooftop solarrooftop solar0.3approved, not builtupdated Jun 2021Jun 2021granted Aug 2021Jun 2021Manchester4.1
Central Park Solar photovalticsrooftop solarrooftop solar0.1operationalupdated Jul 2021Jun 2021granted Sep 2021Jul 2021Manchester4.2
Manchester Communication Academy, Silchester Driverooftop solarrooftop solar0.3approved, not builtupdated Sep 2023Aug 2023granted Sep 2023Sep 2023Manchester4.2
Sainsburys Supermarket, Regent Roadrooftop solarrooftop solar0.3approved, not builtupdated Nov 2025Aug 2025granted Sep 2025Nov 2025Salford4.6
Reliance Trading Estate,Reliance Streetrooftop solarrooftop solar0.4approved, not builtupdated Aug 2023Jun 2023granted Aug 2023Aug 2023Manchester4.6
Herrod Avenue, South Reddishbattery storagebattery storage—application withdrawnupdated Jun 2024Dec 2023—Jun 2024Stockport4.8
Brunel Avenuerooftop solarrooftop solar0.2application submittedupdated Feb 2026Jan 2026—Feb 2026Salford5.3
Metrolink Trafford Depot, Warwick Road Solar Arraysrooftop solarrooftop solar0.3approved, not builtupdated Feb 2022Jan 2022granted Mar 2022Feb 2022Trafford5.6
Metrolink Trafford Depot Solar Panels & Battery Storagerooftop solarrooftop solar0.3refusedupdated Dec 2021May 2021refused Jul 2021Dec 2021Trafford5.6
Metrolink Trafford Depot Solar Panels & Battery Storagebattery storagebattery storage—refusedupdated Dec 2021May 2021refused Jul 2021Dec 2021Trafford5.6
Laurus Ryecroft High School, Lumb Lanerooftop solarrooftop solar0.3approved, not builtupdated Sep 2025Jul 2025granted Sep 2025Sep 2025Tameside5.7
Morrisons Superstore, Saxon Streetrooftop solarrooftop solar0.5approved, not builtupdated May 2024Mar 2024granted May 2024May 2024Tameside6.0
Broughton Hub, Rigby Streetrooftop solarrooftop solar0.2approved, not builtupdated Nov 2024Sep 2024granted Nov 2024Nov 2024Salford6.1
The Albion Academy, London Streetrooftop solarrooftop solar0.2approved, not builtupdated Nov 2025Aug 2025granted Oct 2025Nov 2025Salford6.1
A G Parfett and Son, Didsbury Roadrooftop solarrooftop solar0.3approved, not builtupdated May 2023Apr 2023granted May 2023May 2023Stockport6.2
Heaton Norris Solar PV Panelrooftop solarrooftop solar0.2approved, not builtupdated May 2022May 2022granted Aug 2022May 2022Stockport6.3
Decathlon, Georges Roadrooftop solarrooftop solar0.1approved, not builtupdated Apr 2024Mar 2024granted Apr 2024Apr 2024Stockport6.3
Mercedes Benz, Heaton Merseyrooftop solarrooftop solar0.2approved, not builtupdated Aug 2023Jun 2023granted Jul 2023Aug 2023Stockport6.3
Scotscroft Towers Business Park, Wilmslow Roadrooftop solarrooftop solar0.1approved, not built may be out of dateupdated Feb 2024Jan 2024granted Feb 2024Feb 2024Manchester6.3
Longford Park School, Cromwell Roadrooftop solarrooftop solar0.4approved, not builtupdated Dec 2022Nov 2022granted Dec 2022Dec 2022Trafford6.4
Land at Wrigley Headsolar farmsolar farm0.9under constructionupdated Mar 2026Mar 2020granted Dec 2021Mar 2026Manchester6.5
Burlington Streetrooftop solarrooftop solar0.9approved, not builtupdated Jan 2024Nov 2023granted Jan 2024Jan 2024Tameside6.6
Tudor Industrial Estate, Ashton Street- Micro Energy Storagebattery storagebattery storage0.2approved, not builtupdated Oct 2025Jun 2025granted Sep 2025Oct 2025Tameside6.6
Audi Stockport, Brinksway, Edgeleyrooftop solarrooftop solar0.3operationalupdated May 2022May 2022granted Oct 2023May 2022Stockport6.7
Life Leisure Grand Central, Grand Central Squarerooftop solarrooftop solar0.2approved, not builtupdated Jan 2023Sep 2022granted Dec 2022Jan 2023Stockport6.9
Gamma Telecom, Second Avenuerooftop solarrooftop solar0.2approved, not builtupdated Dec 2025Jul 2025granted Sep 2025Dec 2025Trafford7.1
Fifth Avenue, Trafford Parkrooftop solarrooftop solar0.3approved, not builtupdated Jun 2022May 2022granted Jul 2022Jun 2022Trafford7.4
Concordiarooftop solarrooftop solar0.2approved, not builtupdated Jan 2024Nov 2023granted Jan 2024Jan 2024Tameside7.4
CHEP Manchester, Trafford Parkrooftop solarrooftop solar0.3approved, not builtupdated May 2024Mar 2024granted Apr 2024May 2024Trafford7.4
Rrg Toyota, St Marys Wayrooftop solarrooftop solar0.2approved, not builtupdated Apr 2025Jan 2025granted Mar 2025Apr 2025Stockport7.4
Pisces, Mosley Road, Unit Brooftop solarrooftop solar0.2approved, not builtupdated Mar 2026Dec 2025granted Feb 2026Mar 2026Trafford7.5
Bird Hall Lane, Cheadle Heathrooftop solarrooftop solar0.5approved, not builtupdated May 2026Dec 2025granted Mar 2026May 2026Stockport7.6

28 more projects not listed (furthest or smallest).

Distance from the average position of the M12 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm303002.5
Rooftop solar845667324.9
Floating solar100100
Wind turbine100000
Battery storage2311821601

MW in pipeline: pending, approved and under-construction capacity.

How Manchester decides solar, wind and battery applications

ApplicationsManchesterUK
Decided applications (solar, wind, battery)5010,236
Refused4 (8%)19%
Solar refused4 of 4812%
Onshore wind refused0 of 145%
Battery storage refused0 of 116%
Median time from submission to decision7.6 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

All projects in Manchester

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near M12, 8 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.